Work is in progress on the two-point five kilometers Port Harcourt Road, Fegge Onitsha.
When ABS arrived the site, both drainage construction and rehabilitation, earth work, stone base and removal of unsuitable materials were going on simultaneously on the road.
Speaking to ABS Works Correspondent Ngozi Obileri, the Project Manager, Engineer Ola King said that the road has ten-point three meters carriage way with one meter walk way.
Engineer King explained that the work which started in October is expected to be completed by 20th of December 2023, noting that they were working hard to meet the time schedule
He said they are laying kebbs on areas where drainage has been completed and working to remove the two meters deep unwanted materials on one part of the road.
A resident of the area Mr Chukwuebuka Obiakor thanked Governor Chukwuma Soludo for keeping his campaign promises to Ndi Anambra as he said all the roads under construction presently are of high quality.